Abstract
Construction production is steered with the help of monitoring task progressions and comparing them to the schedule. Construction monitoring is often imprecise. Especially in takt pro-duction, more detailed and systematic monitoring methods should be pursued. In takt production, production must be monitored frequently to make sure that the production follows the takt sched-ule. However, takt production monitoring methods have not been discussed in literature. In this study, a digital monitoring solution for takt production is developed and tested in a case apartment renovation project in Finland. At first, the production monitoring in the case project was done in paper format. This monitoring form was then developed into a digital monitoring application. The progression of production tasks was entered into the application manually. These entries were then automatically compared with a digital takt schedule. As a result, production status can be analyzed automatically and provide diverse information for the construction foremen. This information can be automatically visualized and used as a detailed status report for site meetings. Gathered information can also be revisited afterwards for development or reclamation purposes, for example.
Original language | English |
---|---|
Article number | 92 |
Pages (from-to) | 1-18 |
Number of pages | 18 |
Journal | Buildings |
Volume | 11 |
Issue number | 3 |
DOIs | |
Publication status | Published - Mar 2021 |
Publication type | A1 Journal article-refereed |
Keywords
- Case study
- Lean construction
- Production monitoring
- Refurbishment
- Renovation
- Takt planning
- Takt production
Publication forum classification
- Publication forum level 1
ASJC Scopus subject areas
- Civil and Structural Engineering
- Architecture
- Building and Construction